Preliminary Development Budget

Stadium Construction$789,000,000
Construction Contingency79,000,000
868,000,000
Site Work31,000, 000
Offsite Work8,000,000
Insurance & Project Mgmt.34,000,000
SCSA & City Costs7,000,000
Design & Engineering20,000,000
Permits, Fees & Inspection18,000,000
Professional Fees & Audit3,000,000
Marketing31,000,000
Total Estimate$1,020,000,000