ARTICLE 6. DEVELOPMENT BUDGET AND FINANCING PLAN

Section 6.l . Budget and Financing Plan Overview. The Parties have agreed on a Preliminary Development Budget and Preliminary Financing Plan, although it is recognized that both are preliminary and will be further developed and refined as described in this Article 6. In conjunction with the preparation of Design Development Documents and GMP Set, as described in Article 5 above, Stadco will have lead responsibility for refining cost estimates and developing the Final Development Budget. The Stadium Authority and Stadco shall work cooperatively to develop a Final Financing Plan. As further set forth in this Article 6, the Stadium Authority's approval of the Final Development Budget and Final Financing Plan constitute conditions to the Close of Escrow. The Executive Director may, in her sole discretion, present any matter contained in this Article 6 to the Board for its approval or disapproval.

Section 6.2. Development Budget.

Section 6. 3. Financing Pan.

Section 6.4. Funding Agreement. At or prior to the Close of Escrow, the Stadium Authority, Stadco, the CFD and each lender identified in the Final Financing Plan shall enter into the Funding Agreement which will set forth the terms and conditions for the use and disbursement of the funds set forth in the Final Financing Plan. The Funding Agreement shall be consistent with the Final Financing Plan and the terms of this Agreement and shall include limitations satisfactory to the Stadium Authority on draws on any Stadium Authority Financing prior to the establishment of the GMP. The Funding Agreement shall require the establishment of one or more accounts into which all funds identified in the Final Financing Plan to pay Development Costs shall be deposited, and from which such funds shall be disbursed (collectively, the "Development Fund"). The Funding Agreement shall also describe records maintenance, accounting, audit and other relevant procedures with which the parties to the Funding Agreement shall comply.

Section 6.5. Construction Cost Overrun. Stadco will be responsible to pay the amount, if any, by which the total, actual Development Costs incurred by the Stadium Authority exceed the amount of such costs set forth in the approved Final Development Budget (a "Cost Overrun"). Prior to the Close of Escrow, Stadco and the Stadium Authority shall negotiate and approve the form of the Cost Overrun Commitment.

Previous

Contents

 Next